Wuhai 200 m³/day lightweight block production line

The Wuhai lightweight-block line progressed through final installation and commissioning in March 2025 and entered production in early April. HENGDE’s equipment connects mixing and pouring, mould handling and cutting at the customer factory.

Independent engineeringEquipment manufacturingProject delivery
REAL WUHAI PROJECT MEDIAConnected project equipment shown in the Wuhai customer factory
Three-station vertical cutting equipment at the Wuhai project site
HENGDEProject-specific configuration
01
PROJECT MEDIA

Cutting, connected equipment and material preparation

Connected lightweight block production equipment at the Wuhai project site REAL PROJECT-SITE PHOTO
01

Connected production equipment

A wide site view documents the connected transfer, cutting and downstream handling route.

Three-station vertical cutting equipment at the Wuhai project site REAL CUTTING-EQUIPMENT PHOTO
02

Three-station cutting

The project record includes the installed three-station vertical cutting section.

Material mixing and pouring equipment at the Wuhai project site REAL PROCESS PHOTO
03

Mixing and pouring

A separate site image documents material preparation and pouring equipment in operation.

02
PROJECT BASIS

The 200 m³/day figure belongs to the supplied Wuhai record

Actual output remains dependent on the confirmed product, raw materials, curing conditions, shifts and operating management.